Perbandingan Estimasi Biaya Struktur Gedung Berdasarkan Standar Nasional Indonesia 2008 Dan Analisis Harga Satuan Pekerjaan PUPR 2024 Pada Gedung It Center Universitas Khairun
DOI:
https://doi.org/10.33387/josae.v9i2.12948Keywords:
construction cost estimation,, unit-price analysis, , structural work,, cost deviation, , building cost.Abstract
Cost estimation is a crucial aspect of construction project planning because it affects budget control and the success of project implementation. Differences in unit price analysis methods can result in variations in the Cost Budget Plan (RAB), primarily due to differences in the resource coefficients used. This study aims to analyze the differences in cost estimates for the structural work of the Khairun University Information Technology (IT) Center based on the 2008 Indonesian National Standard (SNI) method and the 2024 Ministry of Public Works and Public Housing (PUPR) Unit Price Analysis (AHSP) method, as well as to identify the factors causing differences in estimated values between the two methods. This study employs a quantitative descriptive approach using a comparative method. The research data consist of project documents, including shop drawings, work volumes, Cost Budget Plans (RAB), and unit price analysis standards based on SNI 2008 and the PUPR 2024 Unit Price Analysis (AHSP). The analysis was conducted by recalculating the structural work costs using both methods, then comparing the estimation results based on the absolute difference and the percentage difference in costs. The results show that the cost estimate for structural work based on the SNI 2008 method was Rp4,350,262,415.78, while the AHSP PUPR 2024 method yielded an estimate of Rp2,663,160,955.24. The difference in estimated values between the two methods was Rp1,687,101,460.54, or 38.78%. These differences are influenced by variations in the unit price analysis coefficients for construction work, particularly for the labor, materials, and equipment components. The research results show that the use of different unit price analysis methods affects the estimated cost of structural work. Therefore, the selection of an estimation method must take into account the suitability of the analysis standards to the project’s characteristics so that construction cost planning can be carried out more accurately.
Downloads
References
[1] M. W. Fazil, C. K. Lee, and P. F. M. Tamyez, “Cost estimation performance in the construction projects: A systematic review and future directions,” International Journal of Industrial Management, vol. 11, no. 1, pp. 217–234, 2021, doi: 10.15282/ijim.11.1.2021.6131.
[2] M. Sayed, M. Abdel-Hamid, and K. El-Dash, “Improving cost estimation in construction projects,” International Journal of Construction Management, vol. 23, no. 1, pp. 135–143, 2023, doi: 10.1080/15623599.2020.1853657.
[3] S. Bayram and S. Al-Jibouri, “Cost forecasting using RCF: A case study for planning public building projects costs in Turkey,” International Journal of Construction Management, vol. 18, no. 5, pp. 405–417, 2018, doi: 10.1080/15623599.2017.1333399.
[4] A. O. Daoud, S. Osama, A. E. Zhairy, and A. G. Mohamed, “Navigating market volatility: Determinants of cost-estimation accuracy in Egypt’s construction sector,” International Journal of Construction Management, published online Aug. 8, 2026, doi: 10.1080/15623599.2026.2714993.
[5] Direktorat Jenderal Bina Konstruksi, “Surat Edaran Direktur Jenderal Bina Konstruksi Nomor 68/SE/Dk/2024 tentang Tata Cara Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum dan Perumahan Rakyat, Lampiran VI: Analisis Harga Satuan Pekerjaan Bidang Cipta Karya dan Perumahan,” Kementerian Pekerjaan Umum, Jakarta, Indonesia, 2024.
[6] K. A. Ratag, G. Y. Malingkas, and J. Tjakra, “Perbandingan rencana anggaran biaya antara metode SNI dengan metode AHSP pada proyek gedung pendidikan Fakultas Teknik Jurusan Teknik Sipil Universitas Sam Ratulangi,” TEKNO, vol. 19, no. 79, pp. 299–305, 2021, doi: 10.35793/jts.v19i79.38754.
[7] N. Alami, U. A. Aziz, and D. Margiarti, “Studi komparasi perbandingan rencana anggaran biaya antara metode analisa harga satuan pekerjaan (AHSP) dan standar nasional Indonesia (SNI),” Surya Beton: Jurnal Ilmu Teknik Sipil, vol. 5, no. 1, pp. 10–19, 2021.
[8] P. Wijaya and M. Giatman, “Perbandingan rencana anggaran biaya menggunakan metode BOW, SNI 2008 dan AHSP 2022 (studi kasus: proyek pembangunan Masjid DPRD Provinsi Sumatera Barat),” Jurnal Applied Science in Civil Engineering, vol. 4, no. 4, pp. 404–408, 2023, doi: 10.24036/asce.v4i4.88583.
[9] E. Kasoma and V. H. Puspasari, “Studi perbandingan analisa harga satuan pekerjaan tahun 2016 dan 2022 bidang Cipta Karya,” Jurnal Basement: Jurnal Teknik Sipil, vol. 1, no. 2, pp. 141–148, 2023, doi: 10.36873/basement.v1i2.10733.
[10] E. Y. Rahmadani, B. Djatmiko, and M. Wena, “Studi komparatif analisa harga satuan pekerjaan struktur beton analisa proyek, metode kondisi aktual, SNI 2016 dan Permen PUPR No. 1 Tahun 2022 menggunakan software Estimator.id,” Bangunan, vol. 26, no. 2.1, 2021. [Online]. Available: https://journal2.um.ac.id/index.php/bangunan/article/view/53245.
[11] M. S. Saputra, Munardy, and Hanif, “Analisis perbandingan rencana anggaran biaya pembangunan Gedung Kuliah Terpadu IAIN Langsa menggunakan AHSP 2024 dan SNI 2013,” Bissotek: Jurnal Bisnis, Sosial, dan Teknologi, vol. 15, no. 2, pp. 69–77, 2025.
[12] G. Y. Nugraha, Lendra, V. H. Puspasari, and T. W. A. Cahyanti, “Analisis perbandingan RAB bangunan gedung dengan AHSP 2016 dan AHSP 2022,” Musamus Journal of Civil Engineering, vol. 5, no. 2, pp. 56–60, 2023.
[13] E. R. Ahadian, N. Nagu, and T. Manuputty, “Model estimasi biaya konstruksi gedung perkantoran di Kota Ternate dengan metode cost significant model,” Jurnal Sipil Sains, vol. 8, no. 15, pp. 11–20, 2018.
[14] Badan Standardisasi Nasional, SNI 2835:2008, Tata cara perhitungan harga satuan pekerjaan tanah untuk konstruksi bangunan gedung dan perumahan. Jakarta, Indonesia: BSN, 2008.
[15] Badan Standardisasi Nasional, SNI 2836:2008, Tata cara perhitungan harga satuan pekerjaan pondasi untuk konstruksi bangunan gedung dan perumahan. Jakarta, Indonesia: BSN, 2008.
[16] Badan Standardisasi Nasional, SNI 7393:2008, Tata cara perhitungan harga satuan pekerjaan besi dan aluminium untuk konstruksi bangunan gedung dan perumahan. Jakarta, Indonesia: BSN, 2008.
[17] Badan Standardisasi Nasional, SNI 7394:2008, Tata cara perhitungan harga satuan pekerjaan beton untuk konstruksi bangunan gedung dan perumahan. Jakarta, Indonesia: BSN, 2008.
[18] H. M. Toma, A. N. Abdelazim, and A. H. Ibrahim, “Assessment of estimation performance for activities’ cost and time in construction projects using statistical process control,” Engineering, Construction and Architectural Management, vol. 33, no. 4, pp. 2669–2695, 2026, doi: 10.1108/ECAM-08-2024-0995.
[19] P. Wang, K. Wang, Y. Huang, P. Fenn, and I. Stewart, “Auditing construction cost from an in-process perspective based on a Bayesian predictive model,” Journal of Construction Engineering and Management, vol. 148, no. 4, Art. no. 04022003, 2022, doi: 10.1061/(ASCE)CO.1943-7862.0002253.
[20] A. H. Turkyilmaz and G. Polat, “Risk-based completion cost overrun ratio estimation in construction projects using machine learning classification algorithms: A case study,” Buildings, vol. 14, no. 11, Art. no. 3541, 2024, doi: 10.3390/buildings14113541.
[21] A. M. Kamaruddeen, C. F. Sung, and W. Wahi, “A study on factors causing cost overrun of construction projects in Sarawak, Malaysia,” Civil Engineering and Architecture, vol. 8, no. 3, pp. 191–199, 2020, doi: 10.13189/cea.2020.080301.
[22] R. Farshidpour, K. Negoro, and F. M. Tehrani, “A statistical approach to analyzing engineering estimates and bids,” Stats, vol. 4, no. 1, pp. 62–70, 2021, doi: 10.3390/stats4010005.
[23] O. Afana, R. Al Zubaidi, S. Abu Dabous, and F. Ibrahim, “Categories and factors of cost overrun in construction projects: A systematic review,” Engineering, Technology & Applied Science Research, vol. 14, no. 6, pp. 18330–18347, Dec. 2024, doi: 10.48084/etasr.9006.
[24] S. Alshihri, K. Al-Gahtani, and A. Almohsen, “Risk factors that lead to time and cost overruns of building projects in Saudi Arabia,” Buildings, vol. 12, no. 7, Art. no. 902, 2022, doi: 10.3390/buildings12070902.
[25] M. H. Al Ahmad, R. Arifuddin, and M. A. Abdurrahman, “Cost overrun factors in construction projects: A BIM and SEM analysis,” Engineering, Technology & Applied Science Research, vol. 16, no. 2, pp. 33365–33374, 2026, doi: 10.48084/etasr.14744.
Downloads
Published
How to Cite
Issue
Section
License

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
License
Articles in JOSAE are published under the Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License (CC BY-NC-SA 4.0). Anyone may share and adapt the work under the following terms: